Tuesday, June 14, 2011

Wednesday, June 8, 2011

Fence Going Up

In accordance to state requirements the fence is being extended to encompass the new well head. One neighbor pitched in to help. Thank you Peggy!

36 Hour Test

This morning began the 36 hour test which will entail sending 3 bacterial samples and a comprehensive panel (metals, etc..). In addition, personnel will be on site to monitor well water depth readings every hour.
A squirrel is grabbing a quick sip of water from the well water runoff. She seemed to approve.

Friday, June 3, 2011

Flushing

The new well is now being flushed. The water will be tested several times and once that is cleared well #2 can be hooked into our current system.

Wednesday, June 1, 2011

Base Meter

Once the city of Southlake signed off on the electric setup, Tri County came in and installed the base meter and did the final connection the power pole. We are one step closer finalizing work on the well.

Sight Glass

The sight glass for the pressure tank has been updated. The tube was procured online easily, but the original connections for it proved much more difficult. It has now been reworked with fittings easily found at Home Depot.

Here is the final setup for the chlorination system. The storage unit came from Home Depot. It fits 2 chlorine barrels perfectly and was the best solution to protect them from the elements, but still have easy access.